Mural and Main Street park improvement to come to Five Corners

Posted

ESSEX JUNCTION — As the days get darker, the City of Essex Junction is working on brightening things up downtown. 

‘We are Essex Junction’ final mural design approval 

The idea for the “We are Essex Junction” mural began before the city and town separation, but it wasn’t until the Connect the Junction Master plan was formed that the mural project took off. City councilors approved a final design for the mural Oct. 14. 

“It was kind of an interesting process because we went out to the kids in the schools and asked them what their thoughts were to ‘We are Essex Junction,’” Council President Amber Thibeault, who was on the project committee, said. “Some drew and some put words to paper. It was all over the place, but it was interesting to see all the different angles the kids came to.”

Artist Matt Heywood's design, based on input from students and Junction residents, features flowers from around the world, emphasizing the diversity in Essex Junction. Heywood is painting the mural on weather-resilient canvas to be installed in pieces onto the southeast-facing wall of the fire station at 3 Pearl Street. 

City councilors also approved city staff applying to a Vermont Arts Council Animating

Infrastructure Implementation Grant for $15,000. This grant would fully fund the mural. 

In order to keep the mural within budget, the mural will only cover parts of the fire station wall. 

Councilor Tim Miller asked if the city had plans to repaint the fire station wall prior to installation of the mural as the current paint color has faded. 

The council and city management did not have a timeline or response as to if or when the city or fire department will repaint the southeastern wall. 

The VAC would potentially award the Animating Infrastructure Implementation Grant in Aug. 2027. Production of the mural on the canvas would span from Aug. to Oct 2027 with installation in late May or early June 2028. 

Councilor Bethany Clark made the motion to approve the final design and accept the grant, if awarded. The motion passed unanimously. 

Main Street park revised scope

The city had previously made plans to redesign the sitting area and park space on the corner of Main Street in Five Corners. 

In 2023, the city received a $200,000 Downtown Transportation Fund grant to support the park’s revitalization. At the time, the council approved a design with a $240,000 budget including a city match of $40,000. Recent quotes estimate the complete design to cost $422,000.

The Main Street Pocket Park started as a grassroots effort in 2022 when community membersworked to make a slice of Five Corners more inviting.

The council decided the city will continue to work on the beautification project, scaling down changes to keep costs at a minimum.

Thibeault made the motion to authorize an additional $182,000 from the economic development fund. The motion passed 3:1, with Councilor Brian Shelden dissenting and Councilor Raj Chawla absent. 

The DTF grant expires on April 30, 2027. 