Town of Essex sets FY25 water and sewer budgets and rates

Posted

ESSEX TOWN — The selectboard unanimously approved the Town of Essex fiscal year 2025 proposed water and sewer budgets Monday night. 

The approved $1.75 million FY25 Town water budget includes an overall cost increase of 7.1% in budgeted line items resulting in a rate increase of 2.99%.

The retail water rate is $6.36 per 1,000 gallons of metered usage, up from $6.18 per 1,000 gallons of metered usage from FY24. The minimum water charge is set to change from $190 to $210 per year. 

There is no proposed change in the water connection fee, which will remain at $5.90 per 1,000 gallons of purchased capacity. 

The approved $2.09 million FY25 Town sewer budget includes an overall cost increase of 9.2% in budgeted line items resulting in a rate increase of 4.8%. 

The retail sewer rate is $11.43 per 1,000 gallons of metered usage. There is no proposed increase in the sewer connection fee, which will remain at $10.60 per 1,000 gallons of purchased capacity. 

An average residential household in the Town connected to both water and sewer, using 200 gallons of water per day, would see an annual increase of $51.72, or a monthly increase of $4.31. This is a 4.15% increase in residential charges for the year over FY24. 

As for the reason for the cost increases? According to a memo from Town public works director Aaron Martin, Town water quality director Annie Costandi and finance director Daniel Roy, water treatment costs from the Champlain Water District make up some of the largest expenses, at 46.7% of the total water budget. 

Costs for repair and maintenance of the Town water system are also increasing by $18,000 in the new FY25 budget to “reflect the actual costs associated with maintenance work,” according to the memo. 

Increases in the FY25 sewer budget are attributed to three main factors: sewer treatment costs from the City of Essex Junction’s wastewater treatment plant, increased costs associated with investigating and monitoring sewer system infiltration and the continuation of a pump station operation and maintenance contract with local pumps and controls specialists Champlin Associates.

Selectboard vice chair Andy Watts moved at the Monday night meeting to approve the new FY25 water and sewer budget. With the motion being passed 5-0, no further comment was brought forth from the public.