The veins of the city: Iroquois Avenue waterline job wraps up

Posted

ESSEX JUNCTION — One of the city’s big capital projects of the year has officially concluded. 

Though smaller than the recent Crescent Connector project and last year’s Main Street waterline replacement, the Iroquois Avenue waterline replacement project took a fair bit of funds, focus and coordination to overhaul this past summer and fall. 

“It's underground,” Public Works Superintendent Rick Jones said. “Nobody sees it. As long as they get up in the morning, turn their faucet on, water comes out, goes down, goes away — everybody's happy. Something like that doesn't work? Yeah, no, they're not happy.” 

Over the span of the last decade, the city did seven-hour isolated spot treatments on Iroquois. 

“We had a fair amount of water breaks on it, five to seven over the last seven to 10 years,” he said. “To fix those, we had to routinely shut it down. It broke and the water bubbled up on the ground, so we had to shut the water down. It affected a fair amount of people, because a lot of our valves in that area aren't working well. It was 70 years-old, I’d guess.” 

But when they realized something systemic was going on with a pipe that appeared to be failing beyond a few spots, with many customers being affected, the full pipe replacement landed a spot on the city’s capital projects priority list. Now, the line is all brand new. 

“Every year, the capital review committee is looking at our whole list of capital projects that are necessary to work on,” said City Manager Regina Mahony. “There's a lot of things on that list, and they're actually scored and ranked… This project rose to the top of the list for FY25.” 

How it all went down 

The project spanned summer through fall 2025, with the final day of construction Nov. 26. It had been on the city’s radar as a need for the last five to seven years and went out to bid and got a contractor signed as preparation last year, before getting installed just recently. 

“It started a little late,” Jones said, glancing at the snow outside. “That's why it got done just right before Thanksgiving, which is good because it was getting close — it was getting real close.” 

In the section where the waterline needed to be replaced, the city put foam under the new street to protect it from frost heaves and increase its longevity. On the rest of the street, they did a “mill and fill,” grinding the old pavement down topped off by an overlay of new pavement. 

Benefits to users in the neighborhood include reliable flow for fire department’s emergency access, as well as vastly improved water quality, better pressure and enhanced volume on account of looping in what was previously a dead-end water line to prevent flow stagnation. 

This line also now has more and newer valves on it, to make any future isolated breaks easier to resolve without impacting more customers along the water main — 10 new valves sit on the reconfigured loop — plus, two hydrants replaced, one of which was not previously functional. 

“We are in decent shape,” Jones said, thinking of the water system city-wide. 

He said the Junction used to be stuck in a cycle of always having to figure out what line was going to be breaking down next, but these days, they’ve nearly caught up, with a few small projects in the queue: remedying a North Street pipe that’s a little undersized, eliminating two dead-end lines under a very small section of Railroad Avenue, as well as updating a very small 280-foot segment of Pearl Street’s waterline — albeit, under a street with much heavier traffic. 

“For bigger projects like that, like when we had the Main Street water line, or the Iroquois, where we have a large project, we do have these daily emails,” Mahony said. “They come through our city engineers because they're the ones out in the field working with the construction company.” 

In those instances, people can subscribe to get up-to-date information about project progress as well as traffic and road closures associated with the project. At the project’s start, they are daily. 

“I personally didn't get many complaints — obviously these guys get them more than I do,” she said, of the construction and engineering team. “We do have a really good relationship with our city engineers to make sure that we're getting the information out to people. And I think we have a good system worked out between all of us to do that.” 

For instance, when certain neighborhoods are affected, there are also door-knocking efforts made in addition to the emails to ensure cars are out of the way when they need to be and that folks know when lanes might be shut down from through-traffic. 

Finishing touches are cosmetic — just checking up on how grass is coming in this spring. 

“It's very good to get that water line fixed and that road opened back up and smoothed,” Jones said. “We appreciate the patience of the people on that road and whoever was affected by the traffic.” 

The contract rang in around $1.28 million to complete the needed Iroquois waterline work. 

What’s around the corner? 

Upcoming projects to watch out for next construction season are slated to be set this budget season, and potentially secured by voters this March. Most likely, some smaller projects like redoing some of the Main Street sidewalk, as well as addressing the Railroad Avenue waterline aforementioned, plus the bigger bus station build. 

It’s possible the waterline on Pearl Street, between West Street Extension and Susie Wilson Road, will get done, followed by a road diet of sorts, although that’s very minimal construction in the grand scheme of things, Mahony said, which would change the existing sidewalk along there into a multi-use path, with an added bus stop and an added mid-block crossing. 

“It is a high traffic road,” Mahony said of Pearl Street. “I would really, really love to say it's 2026 gonna happen, but it's really hard to say whether we're gonna pull that off in time for 2026.”

There is also a resurfacing contract every year, not for complete reconstruction of any road infrastructure, but for some surface repaving throughout the city, to give it some further life. 

Most of these projects are still in conceptual phases and are awaiting precise cost estimates and design specifications, as well as going out to bid and find the best price on a contractor, after which point, the construction schedule will be more clearly fleshed out. 