Five Corners paving starts with Maple St.

Posted

The paving of Maple Street that began over the weekend marks the start of a two-year resurfacing spree around Five Corners.

The Vermont Agency of Transportation got a late start on Maple Street this season, but its contractor, Frank W. Whitcomb Construction Corp. of Colchester, will be held to an October 15 completion date, VTrans engineer Josh Hulett said.

About one mile of Maple Street will be resurfaced from the village/town line near GlobalFoundries to Elm Street, a block before the Five Corners intersection.

Hulett, an Essex resident who uses Maple Street as a commuter route to VTrans headquarters in Montpelier, understands the project’s impact on traffic flow and pedestrians, especially relating to the school day at Albert D. Lawton.

“We are trying to make accommodations for the school, making sure kids and pedestrians have safe passage through the project,” Hulett said.

The agency will hire additional crossing guards to help pedestrians navigate closed sidewalks. There will also be a daily work pause between 6 a.m. and 8:30 a.m. in deference to morning commute hours and the start of school. Work will be ongoing, however, as school lets out and through the evening commute and overnight hours.

At least one lane of Maple Street will remain open at all times, Hulett said.

“We ask motorists to use extreme caution while traveling through the zone. The speed limit will be strictly enforced as the safety of the workers along with the motorists is of the utmost importance,” a VTrans press release states.

Whitcomb is also contracted to pave Lincoln, Main, Pearl and Park streets — the other four spokes of Five Corners — by Aug. 4, 2017. Due to this season’s late start, that paving won’t begin until April, Hulett said.

Paving will be staggered over a 14-week period starting with Lincoln Street.

“It’s going to be a construction zone, but they won’t hold up every avenue [at once],” Hulett said.

Maple Street is first this fall so that it precedes construction on the Crescent Connector road, a Five Corners bypass behind the Lincoln Inn. Crescent Connector construction is set to begin next summer, according to Essex Jct. community development director Robin Pierce.

Another village project that will interplay with VTrans paving is the so-called “missing link” along Pearl Street. The project will widen and add bike lanes to Pearl Street from the post office into Five Corners, widen and resurface sidewalks and add street lighting. It links the pedestrian improvements completed in front of the Champlain Valley Exposition and at Five Corners about seven years ago.

The missing link was originally slated for construction this year, but negotiations on the use of private property for construction stymied the project.

“We can’t get a right-of-way clearance from VTrans to get funds until every property owner has signed,” Pierce said. “It’s just a difficult negotiation.”

Pierce said the village won’t invoke an eminent domain taking of private property for the temporary construction easement. Instead, the project would be redesigned if an agreement is not reached by the time construction is set to begin in the spring.

The missing link project is planned for the spring to allow VTrans to resurface the section in the summer. VTrans’ paving plan for Pearl Street stretches to the West Street Extension near the western village/town line.