ESSEX JUNCTION — The Essex Junction City Council met Feb. 14 to discuss, among other topics, the City’s preliminary fiscal year 2025 enterprise and recreation and parks budgets.
The water, wastewater and sanitation utility rates combined are proposed as of the meeting to have a 6.5% increase from FY24, bringing about a $43.08 increase per year on an average bill.
The preliminary rate change for the water budget from FY24 is 6% in operations and 5.8% in user fees. The wastewater fund is proposed at a 1.1% increase, with an 11.5% increase in user fees.
“This is primarily a result of the flow through the wastewater treatment facility being attributed more to the City than to Essex and Williston compared to previous years,” reads the meeting packet.
The sanitation fund is proposed at a 6.8% operating increase, with a 1.9% increase in user fees.
City finance director Jess Morris told meeting-goers the budget numbers are very preliminary.
“The reason why these are such preliminary numbers is that we only have six months of data right now for water purchase from Champlain Water District, and six months worth of flow data through the wastewater treatment facility,” she said at the meeting. “And this can tend to be a very seasonal fluctuation, so we expect this to definitely change over the next three to four months.”
The meeting’s budget discussion then turned to the capital projects identified in the enterprise funds.
Morris told meeting-goers the water and wastewater capital funds both have sufficient funding projected for several years out at this point in time.
The sanitation capital reserve incorporates upgrades for River Street, Maple Street and West Street pump stations; 50% of the West Street pump station upgrade costs will be covered by the Town.
“The cost of the full engineering and construction of those projects, along with the bonding that would eventually come…that’s ultimately what’s putting the sanitation fund into the negative at this point beginning in FY28,” Morris said.
Morris said City staff is still working with the bond bank and the state on ways to find other funding sources.
Essex Junction Recreation & Parks director Brad Luck was present at the meeting to discuss the budget for EJRP’s program fund.
The program fund represents all anticipated revenues and expenses for EJRP programs and events in the upcoming year. With around 72% of EJRP expenses falling under the program fund, while others go through the general fund, Luck said at the meeting this year’s program fund is projected at a net loss.
With what Luck described as a “healthy” fund balance of $634,827, he said EJRP is looking for where they can use fund balance to fulfill their budget.
“We also have a few unknowns this year that are pretty significant that we think may alleviate this loss and it may not come to fruition,” he said.
One “unknown” is the opening of the new 2 to 3-year-old EJRP Preschool room, set to open in September. Revenue will not begin to be generated until the fall, but that will change in subsequent years, as the program will operate year-round.
Another “unknown” is this year’s change in thresholds and reimbursement rates for licensed child care subsidies.
“Many many more families should qualify…and also the reimbursement rates are increasing drastically, so that should help as well. While we’re proposing a net $98,000 loss, I don’t think that’s where we’ll end up,” Luck said.
The City plans to use the general fund for all senior programming in FY25. The current balance of the separate senior center fund is just under $17,000; this balance will remain separate from all other City funds.
Morris said the intention of this is to see what the future needs of the senior center are after the renovations at 2 Lincoln Street, and to determine what the senior center funds should be used for going forward.
The Essex Junction City Council will meet on Apr. 10 to finalize enterprise budgets. A public hearing to set utility rates will be held on May 22.