Essex Junction City Council discusses 2 Lincoln Street building updates

Posted

ESSEX JUNCTION — Harlan Smith, Essex Junction’s interim City building coordinator, met with City Council March 27 to discuss updates to 2 Lincoln Street, which houses the City municipal offices and other organizations. 

With the renovation plan for the project now 50% designed, Smith and City Manager Regina Mahony took meetingoers through proposed floor plans of each level of the building

The project will currently cost an estimated $2,975,933. With available funds of $2,649,329, either the scope of the project will be reduced to fit into the available funds or additional funds will be needed. 

There is no source of additional funds at this time, according to a memo to City Council from Smith. 

Project updates

Smith told City Council that after taking a look at costs for the first estimate for the project and assessing additional needs for the property, the team adjusted the scope of the project. Project managers are still looking at other ways to make revisions. 

Several updates were made based on a Dec. 21 project estimate. While original plans aimed to upgrade the building to three-phase electric power, the second analysis completed in December aims to leave power in the building as single-phase. 

The original plan also included locating a new HVAC system on top of the roof to maintain basement storage; the new scope has plans to leave the HVAC system residing in the basement. 

The new scope also reduces some previously proposed changes to the building’s lobby, as well as reducing the building’s vestibule to one bay and adding a sewer line lining which Smith said they realized the building needed to have, among another few changes.

Yet with the project still over-budget, another round of attempted cost-cutting completed on Mar. 21 proved a bit more troubling.

This round of cost-cutting includes adjustments like getting rid of the planned lobby vestibule, the sewer line lining, an additional lobby window, a car charging station and other cuts that amount to around $200,000, bringing the costs more in line with existing funds, though still over the amount available. 

Currently, the architect and engineering teams for the project are working on creating 100% construction drawings without this greater, second round of reductions factored in.

“What we felt like when we started to see the second round of reductions from the construction manager, is, we are just nickeling-and-diming these things and trying to pull out some stuff…now we’re sort of struggling with that a little bit,” Mahony said. 

Mahony asked City Council for input on if they feel anything already removed from the scope of the building plan should remain included. 

But she also told the Council there “aren’t really a lot of great sources” for funds to keep additional aspects of the original building plan. 

Council and public comments

City Council president Raj Chawla opened discussion by saying the reductions in scope of the plan are greater than the council previously thought.

“I’d sort of like us to take the approach that we’re trying to do this in a way that we don’t have to return and do it again…we might need to be open to trying to figure out how to find some more money so that we don’t have to make this level of compromise,” Chawla said. 

Chawla advocated at the meeting for keeping public restrooms in the building as part of the plan; he said multiple business owners downtown expressed their interest in that as well, as they are currently serving as the public restrooms.

Council member Andrew Brown said he feels decisions on what should be cut and what should be kept in for the building plan should be determined more so by the needs of staff working in the building. He also expressed a need to start conversations early next year on future building needs.

“In particular, the fire department and public works; have the conversation about going out for a bond sooner rather than later, and having a small portion of that as a part of this project as well,” Brown said. 

Council Clerk Marcus Certa said many things omitted from the updated plan are things he’d like to see included for community engagement and safety and security purposes. In particular, he’s concerned about taking the vestibule off the table based on what he’s heard from community needs. 

Smith told the Council that staff are hoping for full construction documents by the end of April. The project is likely to be out to bid some time in May. 

One community member spoke during public comment to express concern around what will physically happen to the senior center during the building process.

“I’m here for an attempt to get more information to the seniors. We’ve been told that we have to move out at the end of April. And is that really the case with what’s going on with the estimates and the bids and stuff? And what changes are going to be made to the space when we come back?” she asked. 

Mahony said the City offices will move into the senior space during the renovation. 

“Everything that the City is planning for that space is temporary. We’ll go in, we’ll set up our office spaces, all of that temporary stuff will come out,” Smith added. “There are no plans here at this point to make any major changes other than potentially upgrades.” 

Mahony said the City is still working to figure out where senior activities will be hosted during the period of renovation. 

“We’ll be coming to the Council as soon as we’ve got that sorted out, and it will be shared with the seniors as well,” she said. 