Crescent Connector road project set to finish this month

Posted

ESSEX JUNCTION — After a long period of orange construction signs surrounding Essex Junction’s Five Corners, the Crescent Connector project is set to be completed this month.

The estimated $13 million road project, which creates more connectivity throughout the Five Corners, has been in the works for over a decade. Essex Junction City Manager Regina Mahony said the project is one of several “circ alternative projects” to help with traffic congestion issues in Chittenden County.

With Essex Junction’s Five Corners being one of the most heavily trafficked intersections in the state, Mahony told the Reporter the Crescent Connector project is important in helping to  alleviate some of that congestion locally. 

Project construction has taken place over several years. Phase one of the project, which focused on upgrading existing railroad tracks in the Junction, was completed back in 2022. 

Phase two of the project began over a year ago, in May of 2023. This phase of the project created two new signalized intersections that were not in place previously, adding a new roadway from Park Street to Maple Street.

Now, phase two is almost complete. This month, Essex Junction residents can get ready for the opening of the Crescent Connector roadway. 

“These two new signalized intersections, they’ll operate the exact same way the pedestrian signal operates here at the Five Corners…when you want to cross, you can push the pedestrian [button], and it essentially turns all the traffic signals to red lights so you can move free throughout the intersection,” Mahony said. 

Overall, the new roadway will divert drivers traveling beyond Five Corners — to Williston or Essex Town for example — away from the intersection, making more room for pedestrians and cyclists.

Currently, cars traveling up toward the Five Corners from Maple Street can make a left onto Park Street. With the Crescent Connector project, cars will no longer be able to make this left turn if they come all the way to the Five Corners intersection; they can instead use the left turn earlier at the new Crescent Connector roadway.

“We now have all of this length, essentially, stacking length, that will help accommodate that number of people who are trying to get left and trying to go to Williston,” Mahony said. 

There will also be a left turn signal along the Crescent Connector roadway for those coming from Maple Street to turn left onto Park Street from that road. 

The closing of that left lane further up near Five Corners will free up the area for more bike lanes on both sides of the road. Eliminating a phase in the signals at Five Corners can also lead to increased efficiency, Mahony said. 

Cars coming from Williston driving toward Main Street to get to Essex Town will also have a new, free right-hand turn lane onto the Crescent Connector roadway and another right-hand turn lane on Railroad Street onto Main Street, to skirt the traffic at the Five Corners intersection. 

Along with increased efficiency and some new bike lanes, there are other benefits to the project, too, including the creation of a new parking area with two EV chargers.

10 new bike boxes will also be added to the area, for long-term storage of bikes. 

“If somebody living in the City wants to bike here, meet up here with somebody else who’s then going to car commute to Montpelier or something, from this parking lot, they can safely leave their bike the whole day in that spot,” Mahony said.  

As of now, the Crescent Connector project is set to finish construction on Sept. 18, though timelines are always subject to change, Mahony said. 

Following the end of construction, the City plans to host a party to celebrate the opening of the Crescent Connector. For businesses in the area, officials recognize there’s been inconveniences. 

“It’s a disruption, no doubt…I think we are all looking forward to being done so we can at least stop interrupting traffic and folks’ ease of getting in and out,” Mahony said.

#ernltop, crescent connector, essex junction

Comments

No comments on this item Please log in to comment by clicking here